As of 03/28/2024 01:05 PM AKDT
This report includes projects that we anticipate advertising in the next 12 months. Unless otherwise stated, plans and specifications are not available at this time. Please check out the Bid Calendar for projects currently advertising.
Click here to generate an Excel file of the report below.
Region(s):Indefinite delivery / indefinite quantity contract to perform maintenance, repair, and construction work supporting the mission of the Ted Stevens Anchorage International Airport. Contractor shall be responsible for both design and construction work.
more >Install an estimated 70 monitors and 70 input stations with associated hardware, software, and accessories to provide visual paging throughout the South Terminal, Connector, and North Terminal Lobby to meet Americans with Disabilities Act (ADA) requirements.
more >Base Bid: Replace lower roof over 1986 addition (roof 2 on plans), demo skylights, replace vents on new curbs, replace roof to roof seismic joint, provide matching fascia to roof at main entry. Additive Alternate1: Replace roof over original building (roof 1 on plans). Additive Alternate 2: Replace boilers, combustion air intake, and associated misc piping and ducting. Additive Alternate 3: Demo existing siding on original building and 1986 addition. Demo existing wood canopy and existing shed housing air compressor. Re, salvage, protect and store all exterior wall mounted building items not specifically identified for demolition. Demo existing windows at 1986 addition and replace with new windows per contract documents. Provide new exterior lighting at new siding locations. Replace siding at original building and 1986 addition with new weather barrier and profile metal siding. See drawing for wall details. Include replacement of three doors and frames at existing locations.. Additive Alternate 4: Provide new canopy at south side of building and at east exit door. This includes required life safety lighting. Steel frame canopy similar to existing east canopy, low sloped metal roof with snow guards and flexible seismic expansion joint to existing building.
more >The scope of work for this federally funded contract includes the installation of a new Owner-Furnished Controlled Pitch Propeller (CPP) System on the M/V Columbia, including Alarm and Monitoring systems installation, Fire Detection system, testing, and demonstration of acceptable operation to regulatory agencies and the owner. Work includes necessary remediation of contaminated materials, limited engineering, documentation, and State funded annual overhaul work as outlined in the plans and specifications.
more >This state funded includes all necessary construction services as required to replace the existing roof with a new EPDM roofing system at the Peger Road Engineering & Contracts Building at the Department of Transportation Complex at 2301 Peger Road in Fairbanks, Alaska.
more >Rehabilitate the Alaska Highway and construct new passing lanes. Project work will include bridge work, roadside hardware, drainage, intersection improvements and utilities.
more >Pavement preservation, which may include improvements to roadside hardware, drainage, intersections, automated traffic recorders, pedestrian facilities, striping, signs, and utilities.
more >Project will include constructing a new vehicle access control gate at AFM West and install head bolt outlets (HBO) at the TW A and DeHavilland Avenue snow disposal sites.
more >Remove and replace liquid joint sealant and perform cementitious and elastomeric concrete repairs on hardstand RON 2.
more >Provide a drainage system for the lighting duct near the east end of Runway (RW) 7L/25R.
more >Remove and replace approximately 1,000 feet of security fence along the northeast edge of the airfield. Project includes clearing, grubbing, embankment extension and replacing swing gates.
more >This project will design and construct improvements for TW R from approximately TL P to TW Q for Airplane Design Group 6.
more >Rehabilitate approximately 7,000 feet of the tug road from Taxiway Victor to Alaska Cargo Port. Project includes pavement planning, paving, and striping.
more >This federally funded project will rehabilitate approximately 6,000 feet of water pipe around the North Terminal, C Concourse, A Concourse, and Old Airfield Maintenance (OAM) building at the Ted Stevens Anchorage International Airport. Improvements will also include hydrant replacements, valve replacements, and grouting a decommissioned water pipe segment under the South Terminal.
more >This project will rehabilitate the runway, taxiway, apron, and airport access road. The runway safety area will be expanded, and runway grades will be corrected to meet line-of-sight requirements. Additional improvements include replacement of airfield lighting, FAA navaids, wind cones, segmented circle, build a supplemental wind cone access, and apply dust palliative.
more >This contract shall provide for all materials, equipment, supervision, labor, maintenance, fuel, mobilization, and demobilization necessary to clear brush on the State of Alaska Highway facilities within the Anchorage Maintenance District, on an as-needed basis as directed by the DOT&PF Representative. The State may opt to offer renewal of this contract for up to four (4) additional one (1) year period.
more >This federally funded contract is for stormwater infrastructure cleaning services. Work includes cleaning of curb inlets, catch basins, catch basin manholes, manholes, field inlets, lift stations, storm drain pipes and culvert pipes along State of Alaska roadways located in the Kenai Peninsula Maintenance District.
more >Narrative/Scope(if not FHWA)/Explanation for other changes: (New Project - Pre Grant) This project consists of applying new paint and beads to all striping, symbols, crosswalks, and stop bars on state owned roads through out the Southeast District. Any necessary training for State personnel, sweeping, flushing, and any other required pavement preparation where new paint is to be applied. Locations include Juneau, Ketchikan, Klawock, Petersburg, Wrangell, Yakutat. 83% of work is Non-NHS. 17% of work is NHS.
more >Pavement preservation, bridge work, roadside hardware, drainage improvements, and utilities.
more >The Kalsin Bay Maintenance Station was replaced in 2019. The reconstructed facility is a 4100 SQ. Ft. steel frame building with three maintenance bays and an adjoining office, break room, and bathroom. Phase 2 consists of miscellaneous remaining scope required for full functionality of the maintenance station, including but are not limited to, concrete apron replacement, building envelope upgrades, domestic water filtration, wastewater holding tank modifications, fuel tank relocation, provision of an emergency generator, and other mechanical and electrical upgrades.
more >Reconstruct taxiway F and Apron. Replace edge lights, conduit, and cable. Install apron flood lighting along northern end; upgrade light bases and cabling. Significant drainage rehabilitation.
more >Bridge strengthening to NBI#797 at the intersection of Bauer Way and Water Street.
more >This preventative maintenance project will resurface North Eagle River Access Road and may include as necessary; signing and striping, guardrail and other roadside hardware, signalization, lighting, drainage work, dig-outs, bridge repair, curb ramps, automated traffic recorders, and utility relocation.
more >Construct permanent repairs to the Kougarok Road at MP 61.5, MP 66.5, and MP 79.5. Project includes roadway reconstruction and drainage improvements.
more >Reconstruct pedestrian facilities and adjacent areas on 4th Avenue and 11 Avenue in Fairbanks. Project includes drainage improvements, roadside hardware, and utilities.
more >Realign and rehabilitate Seppala Drive in Nome. Work includes pavement rehabilitation, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities.
more >Resurface and widen the state-maintained portion of Woll Road in North Pole. Work also includes drainage improvements, roadside hardware, and utilities.
more >Perform deferred maintenance on the active firing/shooting range at ANC by removing lead bullets and bullet fragments. Amend remaining affected soil with a heavy metal fixation reagent to prevent leaching of lead.
more >This project will design and construct improvements for the North Terminal Northside Aprons and Taxilane.
more >Install a vertical pivot gate to secure the M&O yard at the Old AFM complex and card reader at North Terminal Employee exit.
more >Rehabilitate Postmark Drive from Rockwell Avenue to Dehavilland Avenue. Project includes pavement planning, paving, striping, and drainage.
more >Repair pavement along a section of Runway 7R from the edge of concrete to Taxiway G.
more >Construct a perimeter road along the northwest edge of the security fence. The road will begin just south of the fuel farm and continue around northwest to follow the existing security fence. Project includes structural section, paving, and security fencing.
more >Reconstruct eleven signalized intersections at multiple locations in the City of Fairbanks. Work includes intersection improvements and roadside hardware.
more >Construct drainage improvements at the Deadhorse Airport and along Deadhorse Drive and fill in-fields adjacent to the runway and apron. Construct a wildlife perimeter fence with a service road around the airfield.
more >This project will remove and replace the existing single bay SREB at the same location.
more >Apply new pavement markings, Replace snow removal equipment.
more >Pre Grant Apply new pavement marking and crackseal
more >Apply new pavement markings, Replace snow removal Equipment CC 24300448 LC 33008472 Phase: T02FA1 CC&LC Description: SFAPT00469-2P-Pavement
more >Pre Grant apply new pavement markings and crackseal. Replace snow removal equipment
more >Apply new pavement markings
more >Construct fencing along the boat launch on the Gulkana River.
more >Reconstruction of Haines Highway from Milepost 20 to 25 including the Chilkat River bridge.
more >Provide additional illumination at the Stedman/Deermount intersection to achieve a level of luminance that meets current DOT&PF standards. Construct a concrete sidewalk bulbout on the Stedman side of the marked crosswalk. The bulbout will extend from the existing sidewalk to the edge of the traveled way.
more >This HSIP project will construct a flashing beacon and load center at the intersection of Church Road and Spruce Ave. Work may include drainage improvements, roadside hardware, ADA improvements (curb ramp & pathway), and utilities.
more >This project will replace or rehabilitate the Sayles/Gorge Street Viaduct (#1841).
more >Reconstruct seven signalized intersections at multiple locations in the Fairbanks and Parks Highway Nenana Canyon area. Work includes intersection improvements and roadside hardware.
more >Reconfigure existing parking lot and access roads at Pearl Creek Elementary School in Fairbanks in order to improve vehicle circulation and reduce vehicle idling. Parking lot work includes installation of new vehicle electrical plug-ins, ADA improvements, drainage improvements, paving, and roadside hardware.
more >Replace Nenana DOT Maintenance Station shop roof.
more >Construct a new three bay snow removal equipment building including space for lighting controls and backup generators and a new deicing material storage building.
more >Replace failing culverts on the Hope Highway at MP 7.9 and MP 12.9. Additional improvements may include, as necessary, resurfacing, erosion protection, guardrail, signs, and striping.
more >The work includes excavation, grading, culvert replacement, seeding, rock armoring, and stream channel restoration.
more >This project will construct permanent repairs (PR) to the upper & lower portion of the Waydelich Creek retaining wall. The upper wall was damaged by the December 2020 Storm in the Southcoast Region of Alaska for DDIR AK2021-1 JNS003. Repairs may include, but are not limited to, asphalt, embankment, geotextile, concrete, steel reinforcement, riprap, drainage, roadside hardware, and utilities. Phase code is T02015. The lower wall has years of deterioration & requires additional work to bring the full wall up to seismic code & extend the service life another 40 years. This portion of the project has PM-funding. Phase code is T02A15.
more >Rehabilitate the runway, taxiway, safety areas, apron, and access road. Widen and extend RSA to meet ADG II standards. Place and compact CASC, apply dust palliative. Reconstruct the airfield lighting system, primary wind cone, and supplemental wind cone. Replace rotating beacon on a tip-down pole. Relevel SREB. Construct barge landing.
more >Culvert replacement, drainage improvements, ditch grading, guardrail, signage, utility relocations, clearing and grubbing. This Child Project will construct the first phase of improvements included in the Parent Project CFHWY00592. .
more >Rehabilitate sections of the Shishmaref Sanitation Road and construct erosion control features. Project will include drainage improvements and roadside hardware.
more >Provide additional illumination at the Halibut Point Road/Peterson Avenue Intersection to achieve a level of luminance that meets current DOT&PF standards. Modify adjacent roadway lighting as needed to maintain satisfactory continuous illumination. Establish a pass-through crossing to facilitate less challenging pedestrian movements. Improve intersection sight distance by removing utility equipment located in the southeast quadrant of the intersection, acquiring property to remove parking spaces that, when occupied, create sight line obstructions, and modifying access to an apartment building adjacent to the intersection (shorten curb cut). Replace existing S1-1 School signs with W11-2 advance pedestrian warning signs.
more >This project is for Sitka Seawalk Stage II, which will continue the Sea Walk from the Sitka Public Library to the O¿Connell Lightering Facility. This project would improve pedestrian and ADA accessibility to the existing facilities.
more >Replace automated vehicle gate 3; Replace and widen vehicle gate 9 from 20' to 24'; Replace non-automated vehicle gate 10; Replace locking systems for vehicle gates 3 and 9; Replace locking systems for fence pedestrian gates 4 and 11; Remove vehicle gates 5 and 6 and replace with fence; Replace and relocate pedestrian gate 11; Repair approximately 1200-1500 feet of fence line.
more >Replace runway and taxiway lighting systems, the segmented circle and lighted primary wind cone, and the lighted supplemental wind cone.
more >Project will replace/upgrade access controls and gates to meet 49 CFR 1542 requirements. Replace existing fencing when needed.
more >The Northern Region State of Alaska Department of Transportation and Public Facilities (Department) invites proposals from general construction contractors to serve as "Construction Manager/General Contractor (CMGC)" for Kotzebue to Cape Blossom Road - Stage II. The CMGC procurement is intended to encompass all materials, labor, supplies, equipment and supervision necessary for the complete construction of the project, including any preconstruction related services during the development process.
more >New bridge, drainage improvements, ditch grading, guardrail, signage, utility relocations, clearing and grubbing. This Child Project will construct the second phase of improvements included in the Parent Project CFHWY00592.
more >Begin preliminary design for the Unalaska airport apron and taxiway rehabilitation. For the terminal apron: mill 2 inches of the existing AC pavement and repair underlying PCC. Repave with 2 inches hot mix asphalt. For the hanger apron: repair PCC surface and joints and overlay with 2 inches of hot mix asphalt.
more >This project will construct additional aircraft parking at LHD Echo Parking to replace parking impacted by FAA's new ATCT.
more >Pavement preservation, bridge work, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for DDIR AK 2021 01 JNU002, AK 2021 01 JNU004, AK 2021 01 JNU005, and AK 2021 01 JNU006. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Glacier Highway/Lemon Road, Egan Drive/Glacier Highway, and Glacier Highway/Twin Lakes Drive. This project is funded by FHWA.
more >Pavement preservation, which may include improvements to roadside hardware, drainage, intersections, automated traffic recorders, pedestrian facilities, bridge work, striping, and utilities.
more >This pavement preservation project includes resurfacing, roadside hardware, drainage improvements, bridge improvements, ADA improvements, and utilities as necessary.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for DDIRs AK 2021 01 HNS00l, AK 2021 01 HNS002, AK 2021 01 HNS003, and AK 2021 01 HNS004. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Haines Highway.
more >This project will design and construct a chip seal overlay on Glacier Highway, between Brotherhood Bridge and the Auke Bay Roundabout.
more >Relocate the BLM Road to the Cambell Tract Facility 260 feet to align East 68th Avenue with intersection improvements to include bus stop and integration to existing signalized intersection.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for Disaster Inventory Numbers 461219, 461641, 548035, and 461258. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Mud Bay Road, Sawmill Road, and at the DOT&PF Maintenance Yard. This project is funded by FEMA.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for DDIRs AK 2021 01 HNS005, AK 2021 01 HNS006, AK 2021 01 HNS007, AK 2021 01 HNS008, AK 2021 01 HNS009, AK 2021 01 HNS010, AK 2021 01 HNS011, and AK 2021 01 HNS012. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Haines Highway & Lutak Road.
more >Rehabilitate Ruby Slough Road from Ruby Slough to the landfill. Project will include drainage improvements and roadside hardware.
more >Pavement preservation, bridge work, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities.
more >Project will construct a connection between the Tony Knowles Coastal Trail to the Ship Creek Trail in downtown Anchorage. Major Project Elements include Bridge Work (Pedestrian), Roadside Hardware, Drainage Improvements, Intersection Improvements and ADA Improvements.
more >Rehabilitate Taxiway Echo from Taxiway Victor to Taxiway Lima. Improvements include: provide adequate typical section; evaluate taxiway safety area; replace lighting, markings, and signs; remove, replace, or modify existing storm drainage as needed; and adjust utilities as needed.
more >Replace two damaged culverts with new Aquatic Organism Passage structures across Trout Creek and Little Trout Creek in Cold Bay, AK.
more >Reconstruct Cowles Street from Airport Way through East Cowles Street. Project work will include roadside hardware, drainage improvements, intersection improvements, ADA improvements and utilities.
more >The project will reconstruct the three-leg intersection of Palmer-Fishhook Rd and Trunk Rd. This project may also include roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities.
more >Reconstruct Taxiways C and D at Kodiak Airport, Kodiak, AK. This new project replaces stages 2 and 3 of Kodiak Airport apron and Taxiways C, D, and F reconstruction.
more >Resurfacing and grading the runway, regrading ditches and safety areas, replacement of inoperative culverts and drainage repairs. Installation of new AWOS. CC 24300447 LC 33008462 Phase: T02FA1 LC & CC Description: SFAPT00361-2P-Resurf.
more >Reconstruct the Richardson Highway between MP 167 and 173. Project includes roadside hardware, drainage improvements and utility relocations.
more >Provide a design to improve the function, utilization, and maintenance of the C Concourse Plaza area.
more >Rehabilitate and extend the life of aprons RON 12, 13, and 14 to include joint seal replacement and concrete rehabilitation.
more >Adjust drive lanes at the entrance to provide enough width for maintenance equipment to plow in the vicinity of the access points. Project could include pavement removal and replacement, curb removal and replacement, landscaping, and utility relocations.
more >Rehabilitate approximately 5,000 feet of the Tug Road from Taxiway Alpha to A Concourse. Project includes, pavement rehabilitation, drainage improvements and pavement markings.
more >Resurface Chena Ridge Road and Chena Pump Road. Project will include bridge work, drainage improvements, embankment stabilization, and roadside hardware.
more >Resurface the Glenn Highway from Kings River bridge to Cascade. Additional improvements may include bridge work, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities as necessary. Project construction may be phased.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for Damage Inventory Numbers 461220 - 461221, 461229, 461231 - 461236, 461253, 461255 - 461257, 461652, 784622, and 918887 - 918890. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Beach Road, Front Street, Allen-Menaker Road, Comstock Road, Piedad Road and Mud Bay Road. This project is funded by FEMA.
more >Rehabilitate the pavement of Aircraft and Lakeshore Dr from Voight Cir to the Lake Hood East property boundary south of runway 14/32. Project includes roadway reconditioning, structural section repairs, drainage improvements, and striping.
more >This pavement preservation project will resurface Old Glenn Hwy, Outer Springer Loop and Inner Springer Loop. Additional improvements may also include: utility relocation, roadsidehardward, vegetation clearing, dig-outs, drainage, signs, striping, bridge repairs, ADA improvements, and safety improvements.
more >Make improvements to the AMHS Auke Bay Terminal East Berth. Work would include: Replacement of mooring dolphins, refurbish/replace transfer bridge and support float, install mechanical and electrical upgrades.
more >Reconstruction, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities.
more >Reconstruct Miller Hill Road and Yankovich Road, and improve existing separated multi-use path as needed. Project work will include roadside hardware, drainage improvements, and utilities.